Working backwards from opening day: sequencing a hospitality project

Working backwards from opening day: sequencing a hospitality project

In hospitality the opening date is a commercial commitment — to an operator, to a brand, to a booking engine that is already selling rooms. The construction programme has to be built backwards from it.

Most delayed openings are not caused by a single dramatic event. They are caused by a sequence of small, individually reasonable decisions that each consumed a week of float nobody was tracking.

Start from the operator’s date

Work back from opening through pre-opening staffing and training, systems commissioning, deep clean, snagging, FF&E installation, MEP commissioning and testing. Only what remains is available for construction. If that number is uncomfortable, it is better to be uncomfortable in month two than in month twenty.

Protect the FF&E window

FF&E installation cannot begin until the building is clean, secure and services are live, and it cannot run long because the operator needs the building. It is the most compressible-looking activity in the programme and the least compressible in reality. Procurement dates should be set against the installation window with genuine contingency, not against the shipping estimate.

Commissioning is not a punch list

Testing, balancing and integrated systems commissioning need programme time, specialist attendance and documented sign-off. Treating them as part of snagging is the most common structural error we see in hospitality programmes.

Report against the opening, not the milestone

Every progress report should answer one question first: does the opening date still hold, and what is the evidence? Everything else is supporting detail.

Have a project where this applies? We are happy to look at it with you.
hello@asg-cr.com

Keep reading

Related insights

Leading Vision into Action

Planning a project in Costa Rica?

Tell us what you are building. We will tell you, honestly, what it will take to deliver it — and what it should cost.